Eversource will collect a fee to cover costs of the production meter only. This is part of the application/interconnection process and it will have to be paid before we will issue Permission to Operate. Meter costs range depending which meter fits the need of the project, final meter fees can be found on each utility’s website.
Meter fees:
Voltage/Meter Type | Main Service | Meter Form | Cost |
---|---|---|---|
120/240v Single Phase | Under 400A | Form 2S Bridge | $232 |